Construction Activities Jan. 8 - Jan. 14
Timber Lagging Wall at Harbor Access Road
Pile installation is complete with the majority of piles having been set. Crews began placing the timber lagging between the piles last week and continue to install them this week. The timber lagging is a series of 12x12 pressure treated timber beams stacked in a horizontal configuration between the steel I-beam piles.Timber lagging wall with a portion of the lagging installation completed |
Upper section of lagging wall near boat trailer parking lot |
Lower section of Lagging wall in left turn near Arana Creek |
Example of MSE wall |
Electrical conduit to light trail along wall and causeway |
Lighting Along Timber Lagging Wall
Trenching for the electrical conduit for the timber lagging wall began this week. The conduit will provide power for the 17 light boxes that will be notched in the timber wall, 30 inches above the trail every 30 feet, for the length of the wall down to the Arana Creek causeway (see detail below)
Cross section of multi-use trail along harbor access road |
Multi-Use Trail Construction
The protective plastic has been removed from the pervious concrete multi-use trail and the forms have been pulled. Final grading has begun along both sides of the trail in preparation for hydroseeding.
2. Install baserock and make weather ready
3. Install conduit for lighting
Creek View Trail heading uphill from harbor |
Pervious concrete trail near Hagemann Gulch |
Crews fine tune final grading along the multi-use trail |
Scheduled work for this week
Hagemann Gulch Bridge
1.Excavate bridge footing on east and west side
2. Drill and pour CIDH piles for bridge abutment
2. Drill and pour CIDH piles for bridge abutment
Timber Lagging Wall at Harbor Road
1.Install lagging2. Install baserock and make weather ready
3. Install conduit for lighting
Pervious Concrete Multi-Use Trail
1. Continue work at trail intersection at harbor
2. Re-grade trail for final preparation and hydroseed
2. Re-grade trail for final preparation and hydroseed