Construction Activities Jan. 15 - Jan. 22
Timber Lagging Wall at Harbor Access Road
Crews began placing the timber lagging between the piles last week and continue to install them this week. Backfilling of the wall started this week with the installation of the filter fabric along the back side of the lagging.Crews perform compaction and backfilling for timber lagging wall along harbor access road |
Lighting Along Timber Lagging Wall
Trenching for the electrical conduit for the timber lagging wall has been completed. The conduit has been installed behind the wall and is being backfilled. The conduit will provide power for the 17 light boxes that have been notched in the timber wall, 30 inches above the trail every 30 feet, for the length of the wall down to the Arana Creek causeway.
Light box 30" above finished grade line |
Light box notch-out in timber wall |
Electrical conduit behind wall connecting light boxes |
Light box detail for timber lagging wall |
Cross section of multi-use trail along harbor access road |
Multi-Use Trail Construction
Pervious concrete has been poured at the intersection at the harbor dry storage yard. The intersection will be re-opened after the concrete has cured. The construction fencing will be removed and pulled back up the hill to it's original location. Grading around the intersection will commence to make the paths accessible to all sides. Final grading is proceeding along both sides of the trail along the hill portion and the upper flat sections in preparation for hydroseeding.Remaining section connecting hill and meadow being formed |
Coastal Parie loop trail is temporarily closed this week due to the construction on the Multi-use trail at the midpoint of the meadow. The trail will be reopend after the section is poured and then plated for access.
Coastal Prairie Loop trail (east side) at Agnes Street is temporarily closed due to multi-use trail construction |
Hagemann Bridge abutment on west side
The footings for the west abutment for the Hagemann Gulch Bridge are being excavated. Shoring is also being installed on the west side for the abutment construction.Excavation of footing at west abutment for the Hagemann Gulch Bridge |
Scheduled work for this week
Hagemann Gulch Bridge
1.Excavate bridge footing on east and west side
2. Drill and pour CIDH piles for bridge abutment.
2. Drill and pour CIDH piles for bridge abutment.
Timber Lagging Wall at Harbor Road
1.Finish installing lagging2. Install baserock and make weather ready
3. Backfill wall and bury conduit for lighting
4. Notch wall and install light boxes
Pervious Concrete Multi-Use Trail
1. Pour trail intersection at harbor
2. Re-grade trail for final preparation and hydroseed.
3. Form and pour last section in middle meadow
2. Re-grade trail for final preparation and hydroseed.
3. Form and pour last section in middle meadow