Construction Activities Jan. 7- Jan. 14
Arana Gulch Multi-Use Trail Project
The Arana Gulch Multi-Use Trail Project is underway! The ground breaking is behind us and you can stay on top of how the project progresses by following the blog weekly.
Monday, January 12, 2015
Monday, December 15, 2014
Ribbon Cutting and Dedication
January 14, 2015 2-4 pm
At the Hagemann Gulch Bridge
Join us in celebrating the official opening of the Arana Gulch Multi-Use Trail Project at the Frederick Street entrance. A free family event featuring the Kuumbwa Jazz Honor Band and refreshments. Celebrate with City and County officials and community members. Enjoy environmental and construction tours.
Parking hosted by
Santa Cruz Bible Church
440 Frederick Street
Our Lady Star of the Sea Church
515 Frederick Street
Bike valet parking hosted by People Power of Santa Cruz County
More information:
Please contact the City of Santa Cruz Public Works Department
(831) 420-5160
Wednesday, September 10, 2014
Construction Activities
Construction Activities Sept. 10 - Sept. 17
TRAIL CLOSURE ALERT!
The contractor will be closing the whole western side of Arana (yellow area on map below) to complete the north/south portion of the trail. This work will be approximately 2-1/2 months in duration. The trailhead at Agnes will remain open with access along the eastern trails down to the harbor and to the southern portion of the park. We know this will impact the park users and is an inconvenience, but the end is in sight for the project. Thank you all for your continued patience as we race toward the project completion in November.
Wednesday, August 6, 2014
Construction Activities
Construction Activities Mar. 17 - Mar. 24
Pathway at Frederick Street Underway
Thursday, February 13, 2014
Construction Activities
Construction Activities Feb. 13 - Feb. 19
Curb, Gutter, and Sidewalk Installed at Harbor Access Road
We had some much needed rain last weekend. The contractor had all of their erosion control measures in place and everything in the project held up very well. The work on placing concrete curb, gutter, and sidewalk continued this week along the harbor access road. Crews placed concrete from the large wooden harbor sign, up the hill, to the intersection of Seventh Avenue.Wednesday, February 5, 2014
Construction Activities
Construction Activities Feb. 4 - Feb. 12
Curb, Gutter, and Sidewalk work begins at Harbor Access Road
We've been receiving a lot of great feedback about the work alongside the harbor access road. I know many of you are excited about the sidewalk being installed from 7th Avenue down the hill to the big harbor sign. Work continues with the excavation, compaction and baserock to prepare for the forms to place concrete curb, gutter and sidewalk.Wednesday, January 22, 2014
Construction Activities
Construction Activities Jan. 22 - Jan. 29
Hagemann Gulch Bridge Abutments
With shoring in place work has begun on the excavation of the western bridge abutment behind the Santa Cruz Bible Church on Frederick Street. Crews will continues the excavation this week to prepare for forming the footings and the abutment slab.