Construction Activities Nov. 27- Dec. 4
Happy Thanksgiving everyone! There will be no construction work on 11/28 and 11/29. The construction access road has been completed with the placing of the base rock on the filter fabric underlayment. The road will be used for construction equipment and vehicle access to the western bridge abutment over the course of the next year. The Parks and Recreation Department began construction of the new Marsh Vista trail near the Agnes street entrance. This will be a permanent dirt trail connecting to the other dirt trails on the east side of the meadow. Grading of the trail will begin December 9.
The Arana Gulch Multi-Use Trail Project is underway! The ground breaking is behind us and you can stay on top of how the project progresses by following the blog weekly.
Thursday, November 28, 2013
Wednesday, November 20, 2013
Construction Activities
Construction Activities November 18-22
The construction project continues this week despite the much needed rain we received over the last few days. Progress continues on the construction access road. The Parks and Recreation Department will construct the new Marsh Vista trail near the Agnes street entrance. This will be a permanant dirt trail connecting to the other dirt trails on the east side of the medow (see photos).
The construction project continues this week despite the much needed rain we received over the last few days. Progress continues on the construction access road. The Parks and Recreation Department will construct the new Marsh Vista trail near the Agnes street entrance. This will be a permanant dirt trail connecting to the other dirt trails on the east side of the medow (see photos).
Tuesday, November 19, 2013